Budgeted overheads $493,200 Budgeted machine hours 10,960
January 2nd, 2018
Based on the data below, what is the amount of the overhead under-/over-absorbed?Budgeted overheads $493,200 Budgeted machine hours 10,960 Actual machine hours 10,493 Actual overheads $514,157A. $20,957 under-absorbedB. $21,015 over-absorbedC. $21,015 under-absorbedD. $41,972 under-absorbed