MGT190 – The Theory X approach to managing workers is a classic example

Q1. The Theory X approach to managing workers is a classic example of a top-down view of how people should be managed. a. true b. falseQ2. Ensuring a one-to-one correspondence between specification items and general design items is a feature of: a. Scope statement definition b. WBS construction c. Rapid prototyping d. Configuration managementQ3. The resource planning tool that enables us to identify who we need to carry out what tasks is called: a. A resource Gantt chart b. A resource matrix (also called the responsibility chart) c. A resource ogive d. A resource loading chart (also called a resource histogram)Q4. A major strength of task Gantt charts is that they can: a. Offer a sophisticated model of a project b. Show how many resources will be used on the project c. Show the interdependencies of tasks d. Show actual versus planned schedule statusQ5. Bottom-up estimates: a. Are based on historical trends b. Can be derived from the WBS c. Must employ Monte Carlo simulation d. a and cQ6. Scope creep means: a. Needs emergence and identification b. Uncontrolled changes to a project’s requirements during project execution c. Migration of project needs to requirements d. Imprecise scope statementQ7. Definitive estimates are generally derived from: a. Bottom-up estimates b. Top-down estimates c. Expert judgment cost estimates d. Order of magnitude estimatesQ8. A key weakness of the Benefit-Cost ratio project selection mechanism is that: a. It only focuses on things that can be measured b. It takes time frame into consideration c. It is too much based on subjective judgment d. It does not entail prioritizingQ9. The bottom-most level of the WBS — the level at which project budget and schedule data are captured — is called: a. Work package b. Code of accounts c. Budget baseline d. Change control levelQ10. An effective project manager must: a. Tell his team members what to do b. Be the most capable person on the team technically c. Be focused on achieving results d. Not trust his team members to achieve results without his personal attention to detailQ11. Functional requirements provide us with detailed technical specifications. a. true b. falseQ12. Which of the following is an example of a project? a. Maintaining e-mail addresses b. Capacity planning c. Submitting travel and expense reports d. Sending monthly reports to top managementQ13. Which of the following shows resource allocation over time? a. Resource Gantt chart b. Resource matrix c. S-Curve d. Resource levelingQ14. When we have objective data on the probability of an event, we are involved with decision making under certainty. a. true b. falseQ15. According to PMI, a WBS should focus on a. Tasks b. Deliverables c. Interrelationships among activities d. Cost of the projectQ16. Top-down estimates (also called parametric estimates): a. Are based on historical trends b. Can be derived from the WBS c. Can be determined by analyzing work packages d. Provide accurate assessments of project costsQ17. In risk management, insurance is an example of: a. Risk avoidance b. Risk deflection c. Risk acceptance d. Contingency planningQ18. Rapid prototyping is a methodology for: a. Specifying requirements at the outset and for controlling very tightly any changes to them b. Specifying requirements at the outset and for facilitating later changes to them with minimum customer in put c. Triggering early warning of unauthorized changes to the original prototype to enable project management to take remedial actions d. Working closely with customers by creating and updating prototypes that respond to customer inputQ19. Under what conditions may a project manager accept a change request? a. If the request has no effect on project objectives, deadlines, or resources b. If the request has no effect on project objectives, although it has effects on deadlines and resources c. If the request is coming from a valued customer d. If the request is from the Chief Executive OfficerQ20. A modern view in Human Resource Management is that positive motivation results from an opportunity to achieve and experience self-actualization. a. true b. falseQ21. A challenge of the matrix project organization is that: a. Team members are full of ego b. Team members are selected from the same functional area c. Team members have divided loyalties d. It enables functional managers to provide career guidance to their workersQ22. In resource planning, one of the issues that needs to be considered is: a. Staff empowerment b. Technical requirements of the project c. Theory X management principles d. Theory Y management principlesQ23. In project management, the level of uncertainty plays a major role in determining the adequacy of a project plan. a. true b. falseQ24. A work package is to be found at the summary level of the WBS. a. true b. falseQ25. If review of a project’s status indicates that EV = $400, AC = $400, and PV = $500, the project is: a. On budget, behind schedule b. On budget, ahead of schedule c. Over budget, behind schedule d. Over budget, ahead of scheduleQ26. A laissez-faire management style may lead to a ship without rudder syndrome. a. true b. falseQ27. A project team structure that closely reflects the physical structure of the deliverable is known as: a. Egoless b. Specialty c. Surgical d. IsomorphicQ28. An objective of prototyping is to minimize life-cycle cost. a. true b. falseQ29. A key objective of change control in configuration management is to keep track of actions taken in response to change requests. a. true b. falseQ30. Needs recognition is the first stage of the needs-requirement life cycle. a. true b. falseQ31. A tool that graphically shows cost variance is: a. A chart of accounts b. A code of accounts c. A histogram (also called a resource loading chart) d. A cumulative cost curve (also called S-curve)Q32. Internal Rate of Return (IRR) is the discount rate that sets the present value of cash outflow equal to the present value of cash inflow. a. true b. falseQ33. Structured Walk-Through is a methodology used in: a. PERT b. GERT c. VERT d. Project EvaluationQ34. If you want to shorten the length of a project, you must: a. Shorten the critical path b. Shorten the free float c. Spend more money d. Cut back on the features you plan to deliverQ35. Which of the following is a scope planning tool? a. Benefit/cost analysis b. WBS c. Earned Value analysis d. Fast trackingQ36. A project can be terminated prematurely because the original objectives may no longer be valid. a. true b. falseQ37. When crashing a project, we typically choose critical path tasks whose costs of crashing are highest. a. true b. falseQ38. Using working time or elapsed time to calculate the time it will take to complete a task produces the same results. a. true b. falseQ39. Milestones, like tasks, consume resources. a. true b. falseQ40. A four step risk assessment process reflecting standard risk management good practice consists of: a. Risk identification, Risk deflection, Risk impact analysis, Risk monitoring and control b. b. Risk acceptance, Risk impact analysis, Risk response planning, Risk monitoring and control c. Risk deflection, Contingency planning, Risk impact analysis, Risk monitoring and control d. Risk identification, Risk impact analysis, Risk response planning, Risk monitoring and control

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper
Calculate the price
Make an order in advance and get the best price
Pages (550 words)
$0.00
*Price with a welcome 15% discount applied.
Pro tip: If you want to save more money and pay the lowest price, you need to set a more extended deadline.
We know how difficult it is to be a student these days. That's why our prices are one of the most affordable on the market, and there are no hidden fees.

Instead, we offer bonuses, discounts, and free services to make your experience outstanding.
How it works
Receive a 100% original paper that will pass Turnitin from a top essay writing service
step 1
Upload your instructions
Fill out the order form and provide paper details. You can even attach screenshots or add additional instructions later. If something is not clear or missing, the writer will contact you for clarification.
Pro service tips
How to get the most out of your experience with Essay Fountain
One writer throughout the entire course
If you like the writer, you can hire them again. Just copy & paste their ID on the order form ("Preferred Writer's ID" field). This way, your vocabulary will be uniform, and the writer will be aware of your needs.
The same paper from different writers
You can order essay or any other work from two different writers to choose the best one or give another version to a friend. This can be done through the add-on "Same paper from another writer."
Copy of sources used by the writer
Our college essay writers work with ScienceDirect and other databases. They can send you articles or materials used in PDF or through screenshots. Just tick the "Copy of sources" field on the order form.
Testimonials
See why 20k+ students have chosen us as their sole writing assistance provider
Check out the latest reviews and opinions submitted by real customers worldwide and make an informed decision.
Other
Should have been around social worker in the UK but I can adapt it.
Customer 453101, August 5th, 2022
Education
Very well written thank you
Customer 452667, April 8th, 2021
Nutrition, Hospitality & Human Services
Thank you for your assistance.
Customer 452919, April 13th, 2024
Nursing
Great paper thank you so much
Customer 452667, March 19th, 2021
Sociology
Thank you, I have been averaging 16/20 points for the past discussions 1-4). Unsure why, but I will know how this one goes in a few days. Thank you for your assistance.
Customer 452919, February 16th, 2023
Psychology
Thank you very much! I will be using your service again soon.
Customer 452665, March 18th, 2021
Business Studies
This is fantastic! Thank you so much! Great customer service and help!
Customer 453131, November 15th, 2022
Sociology
Thanks to the entire team!
Customer 452919, December 8th, 2021
Advanced Technical Writing
Excellent service as always, Thank you!
Customer 452995, January 20th, 2022
History
Thanking you all in advance for your assistance.
Customer 452919, November 26th, 2024
Nursing
Fabulous fast service
Customer 453075, April 21st, 2022
Sociology
Thanks to the Team
Customer 452919, March 22nd, 2022
11,595
Customer reviews in total
96%
Current satisfaction rate
3 pages
Average paper length
37%
Customers referred by a friend
OUR GIFT TO YOU
15% OFF your first order
Use a coupon FIRST15 and enjoy expert help with any task at the most affordable price.
Claim my 15% OFF Order in Chat