Project Management-If the cost variance is positive and the schedule variance is also positive
June 8th, 2024
If the cost variance is positive and the schedule variance is also positive, then it indicates that …A. Project is under budget and behind scheduleB. Project is over budget and behind scheduleC. Project is under budget and ahead of scheduleD. Project is over budget and ahead of schedule