Project Management- PMAN 650 Session 5 Individual Assignment Earned Value

Introduction
All of you have had at least an introduction to earned value
management in the project management fundamentals course. Many of you may have
had the opportunity to use earned value management in your professional
careers. In practice, most EVM analysis results are generated by scheduling
software or other applications. As a project manager, you musthave a good
handle on the concepts and be able to verify the accuracy of EVM analysis
results.
In this assignment,
you will have an opportunity to brush up and expand upon your EVM knowledge and
skills by applying EVM concepts to a practical problem. THIS ASSIGNMENT
REQUIRES A MANUAL ANALYSIS – DO NOT USE MICROSOFT PROJECT.
Problem Background
Your project consists of six activities shown in the table
below, along with: (1) planned start and finish dates; (2) activity budgets;
and (3) earned value (EV) accrual rules from you project cost management plan.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

Activity

Planned
Start

Planned
Finish

Budget

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

EV
Accrual Rule

Activity One

Mon – 10/13/14

Fri – 10/31/14

10,000

Percent Complete with Gates

Activity Two

Mon – 10/20/14

Fri -11/28/14

30,000

Fixed Formula -50/50

Activity Three

Mon -11/3/14

Fri -11/14/14

7,000

Fixed Formula -20/80

Activity Four

Mon -10/13/14

Fri -11/14/14

20,000

Weighted Milestones

Activity Five

Mon 11/17/14

Fri – 12/5/14

10,000

Fixed Formula – 0/100

Activity Six

Mon -12/8/14

Fri -12/19/14

7,000

Fixed Formula – 0/100

Activity Two has a start-to-start relationship (one week lag
time) with Activity One. Activity Three has a finish-to-start relationship with
Activity One. Activity Five has finish-to-start relationships with activities
Three and Four. Activity Six has finish-to-start relationships with activities
Two and Five.
Assumptions
1.
Assume a five-day work week.
2.
For all activities (except Activity Four), assume
the expenditure rate is constant over the duration of the activity, i.e.:
.png”>

For Activity Four, assume the expenditure profile shown
below:

.png”>

The project sponsor wants you (the PM) to present a project
cost and schedule performance assessment using data through Friday, Nov 7,
2014. You have collected the following information:

Activity

Actual
Start

Actual
Finish

Actual
Cost

Activity One

Mon – 10/13/14

Fri – 11/3/14

12,000

Activity Two

Mon – 10/20/14

12,000

Activity Three

Mon -11/4/14

4,000

Activity Four

Mon -10/13/14

20,000

Activity Five

0

Activity Six

0

For Activity One, three equally-valued gates have been
established and all gates are complete as of 11/7/14.
For Activity Four, four milestones have been established
with the following values: (1) milestone 1 – 30%; milestone 2- 30%; milestone 3
– 10%; milestone 4 -30%. Three of the milestones are complete as of 11/7/14.
Show all
work. Round dollar values to the nearest dollar. Calculate all other variables
to three decimal places.

1.
Earned Value Measures

a.
Calculate earned value measures for each
activity and for the cumulative project as of 11/7/14; fill in the table below:

Activity

Planned Value (PV)

Earned Value (EV)

Actual Cost (AC)

Activity
One

12,000

Activity
Two

12,000

Activity
Three

4,000

Activity
Four

20,000

Activity
Five

0

Activity
Six

0

Entire
Project

2.
Earned Value Performance Measures

a.
Calculate earned value performance parameters
for each activity and for the cumulative project as of 11/7/14; fill in the
table below:

Activity

Schedule Variance (SV)

Schedule Performance Index (SPI)

Cost Variance (CV)

Cost Performance Index (CPI)

Activity
One

Activity
Two

Activity
Three

Activity
Four

Activity
Five

Activity
Six

Entire
Project

b.
Is the project ahead of schedule, on schedule,
or behind schedule? What information are you using to make this assessment and
why?
c.
Is the project over budget, under budget, or on
budget? What information are you using to make this assessment and why?

3.
Earned Value Forecasts
a.
Calculate the range (low/most-likely/high) of possible
Estimates-at-Completion (EAC).
b.
Using the low EAC, what is the
Estimate-to-Complete (ETC)?
c.
Using the high EAC, how much more or less money
(other than the current budgeted amount) will you need to finish the project?
d.
How much would the Cost Performance Index (CPI)
have to change in order to complete the project within the original budget?

Calculate the price
Make an order in advance and get the best price
Pages (550 words)
$0.00
*Price with a welcome 15% discount applied.
Pro tip: If you want to save more money and pay the lowest price, you need to set a more extended deadline.
We know how difficult it is to be a student these days. That's why our prices are one of the most affordable on the market, and there are no hidden fees.

Instead, we offer bonuses, discounts, and free services to make your experience outstanding.
How it works
Receive a 100% original paper that will pass Turnitin from a top essay writing service
step 1
Upload your instructions
Fill out the order form and provide paper details. You can even attach screenshots or add additional instructions later. If something is not clear or missing, the writer will contact you for clarification.
Pro service tips
How to get the most out of your experience with Essay Fountain
One writer throughout the entire course
If you like the writer, you can hire them again. Just copy & paste their ID on the order form ("Preferred Writer's ID" field). This way, your vocabulary will be uniform, and the writer will be aware of your needs.
The same paper from different writers
You can order essay or any other work from two different writers to choose the best one or give another version to a friend. This can be done through the add-on "Same paper from another writer."
Copy of sources used by the writer
Our college essay writers work with ScienceDirect and other databases. They can send you articles or materials used in PDF or through screenshots. Just tick the "Copy of sources" field on the order form.
Testimonials
See why 20k+ students have chosen us as their sole writing assistance provider
Check out the latest reviews and opinions submitted by real customers worldwide and make an informed decision.
Education
I love you guys, yal are the best. Thank you so much !!!
Customer 453117, September 10th, 2022
Sociology
Thank you for answering all of the questions provided. The last 3 discussions, I only received a grade of 14 out of 20 points. Let's see how it goes after the grades are posted next week.
Customer 452919, February 9th, 2023
Social Work and Human Services
I have no other choice but to approve the order. I have had to edit several statements and grammer.
Customer 452919, April 20th, 2025
Business Studies
This is fantastic! Thank you so much for your hard work!
Customer 453131, November 16th, 2022
Arts and Applied Sciences
I am having to run the paper through my editor, which is a good thing. It allows me to edit any errors.
Customer 452919, January 20th, 2025
History
Thank you for the revision
Customer 452919, October 31st, 2024
Humanities
Best Serivces
Customer 452995, January 24th, 2022
Psychology
Communication on the small delay was appreciated and final result was worth the wait. Thank you.
Customer 452665, March 18th, 2021
Nutrition, Hospitality & Human Services
Thank you for your assistance.
Customer 452919, April 13th, 2024
Sociology
I have never experienced receiving a paper past the due date and time. That is the only thing that displeases. I don't have time o Overall, your team does a great job.
Customer 452919, November 18th, 2021
Nursing
Very good service
Customer 453075, April 27th, 2022
Sociology
I enjoyed the writer's work. Please send the writer's ID. The paper was available ahead of the due date and numbered each question to ensure mee that it was covered. AWESOME WORK!
Customer 452919, April 20th, 2022
11,595
Customer reviews in total
96%
Current satisfaction rate
3 pages
Average paper length
37%
Customers referred by a friend
OUR GIFT TO YOU
15% OFF your first order
Use a coupon FIRST15 and enjoy expert help with any task at the most affordable price.
Claim my 15% OFF Order in Chat