Project Management-Suppose a project consists of the following activities.
January 1st, 2018
2. Suppose a project consists of the following activities.Activity Immediate Predecessors Time (Days)A None 5B None 8C A 4D B, C 6E B, C 4F D 6G E, F 4(a) Draw the activity-on-node (AON) project network based on the table above. Only nodes and directed arrows are required in the network for full credit.(b) List all the paths in the network and calculate the completion time of each path(c) What is the project completion time? Please give the reason for full credit.