Project Management-Volkswagen Mexico Revs Up For Jetta Component Production”

Using the case study below, “Volkswagen Mexico Revs Up For Jetta Component Production”, consider the project management toolbox and the various project management tools. Discuss how these could be applied to support the achievement of strategic objectives in the case study.VOLKSWAGEN MEXICO REVS UP FOR JETTA COMPONENT PRODUCTIONPROJECT MANAGEMENT TECHNIQUES DELIVER RESULTS ON-TIME AND WITHIN BUDGETTo prepare for the production of its new Jetta, Volkswagen turned to a combination ofinternational plants and external suppliers to produce portions of the carís new motor andaxle assemblies.Volkswagen Mexico Components (VW Mexico) won a competitive bid to produce severalmotor and axle parts and assemblies, including the front axles and cornermoduleassemblies. The team at the VW Mexico plant had 21 months and a budget of $3.3 million(US) to design and install the assembly line and begin mass production of parts.BackgroundVW Mexico won the competitive bid for the component assembly project by proposing afixed cost for part production. This meant there would be no room for budget overruns. Anywork that exceeded the budget would be incurred as a loss.The front axle and cornermodule assembly production was overseen by a ProjectManagement Professional (PMPÆ) and the project was one of the first to be managed by theVW Mexico project office, which provided oversight for the entire portfolio of programs andprojects related to the production of Jetta components. The project manager and teamwould have to help develop and introduce internal processes that future teams would follow.In addition, a new supplier was selected for the project while the equipment procurementprocess was underway. This late addition resulted in a two month delay in the acquisition ofthe assembly lines.ChallengesThe VW Mexico team used standard management processes, as described in A Guide to theProject Management Body of Knowledge (PMBOKÆ Guide), to complete the assembly lineproject on-time and under budget.To oversee the complex project, VW Mexico established a project management office (PMO), which was responsible for monitoring and controlling the overall budget and schedules forthe Jetta-related projects. Once VW Mexico was awarded the assembly project, the PMOcoordinated with the finance department to obtain the resources necessary for the project. A project manager was selected and the manufacturing department manager was namedproject sponsor.The project manager, supported by a member of the planning department, integrated theplans submitted by various project participants and developed a work breakdown structure(WBS) and detailed the timeline for the overall project. The WBS served as a roadmap foreach phase of the project. While the manufacturing and quality departments were involvedthroughout the project, other departments could be consulted as necessary. The projectmanager was responsible for overseeing the WBS and involving other departments atappropriate times.SolutionsFrom initiation to closing, the project was divided into five phases with nine milestones overtwo years. The timeline included all work from procurement and fabrication of equipmentthrough assembly line testing and optimization. The final phase ended with the start of axleproduction and cornermodule assembly. In addition, a corresponding quality plan wasdeveloped using the standards of the components plant, which was integrated into thetimeline.The project manager held regular meetings with the core team to keep all departmentsinformed of progress. The assembly line supplier visited the VW Mexico plant on severaloccasions to review progress and provide assistance in addressing any issues. Additionaldepartments were involved when needed, and a project status report ó detailingperformance index to indicate progress relative to the overall timeline and budget ó wasdistributed monthly to all departments. Because of the strict budget adherencerequirements for the project, financial resources were blocked to avoid overruns.In each meeting, participants had the opportunity to request specific changes to the WBS. Discussions were documented for quality purposes and changes were approved by both theproject manager and project sponsor.To ensure the project would be completed on time, the project manager found creativeways to resolve timing issues created earlier in the process: To offset a two month delay inreceiving assembly line equipment, the manufacturing group conducted training while themaintenance group assisted the subcontractor with installation of the assembly lineequipment. By performing these two events simultaneously, the project manager preventedfuture delays that might cause the project to exceed the timeline.Throughout the project, the PMO maintained oversight for the overall budget. Other projectelements were monitored by individual members of the project team. For example, aplanning team member monitored activities related to the WBS and quality plan while aquality team member was responsible for ensuring that the parts being produced metcompany quality specifications.At the completion of each project phase, the project team analyzed the overall projectstatus and conducted risk assessments for the remaining phases. Any resulting changes tothe WBS were approved by the project manager and project sponsor.The end of the project was marked by the transition to full production mode. The officialproject closing took place 12 weeks after initial component production commenced.ResultsThe VW Mexico team achieved and in many cases exceeded the objectives for the assemblyset-up project. Specifically: The entire project was completed within the specified budget  The team met all delivery deadlines for each phase of testing Front axles and cornermodules produced on the plantís assembly lines continuedto meet Volkswagenís quality guidelinesThe Jetta component assembly line project team also developed a number of tools andpractices to serve as standards for future projects at the plant. Key learnings from theproject will enable future project teams to optimize communication between different areasof the VW Mexico plant and ensure the success of future projects.

Calculate the price
Make an order in advance and get the best price
Pages (550 words)
$0.00
*Price with a welcome 15% discount applied.
Pro tip: If you want to save more money and pay the lowest price, you need to set a more extended deadline.
We know how difficult it is to be a student these days. That's why our prices are one of the most affordable on the market, and there are no hidden fees.

Instead, we offer bonuses, discounts, and free services to make your experience outstanding.
How it works
Receive a 100% original paper that will pass Turnitin from a top essay writing service
step 1
Upload your instructions
Fill out the order form and provide paper details. You can even attach screenshots or add additional instructions later. If something is not clear or missing, the writer will contact you for clarification.
Pro service tips
How to get the most out of your experience with Essay Fountain
One writer throughout the entire course
If you like the writer, you can hire them again. Just copy & paste their ID on the order form ("Preferred Writer's ID" field). This way, your vocabulary will be uniform, and the writer will be aware of your needs.
The same paper from different writers
You can order essay or any other work from two different writers to choose the best one or give another version to a friend. This can be done through the add-on "Same paper from another writer."
Copy of sources used by the writer
Our college essay writers work with ScienceDirect and other databases. They can send you articles or materials used in PDF or through screenshots. Just tick the "Copy of sources" field on the order form.
Testimonials
See why 20k+ students have chosen us as their sole writing assistance provider
Check out the latest reviews and opinions submitted by real customers worldwide and make an informed decision.
History
Thanking you all in advance for your assistance.
Customer 452919, November 26th, 2024
Nursing
Very good service
Customer 453075, April 27th, 2022
History
Thank you
Customer 452919, October 28th, 2024
Sociology
Thank you so much. Your Team is the greatest!
Customer 452919, May 3rd, 2022
Tourism
thank you
Customer 452933, November 20th, 2021
English 101
well written excellent job, thank you!!
Customer 452989, December 2nd, 2021
Business Studies
I had no idea what to do here and you nailed it! Thank you so much!
Customer 453131, November 21st, 2022
History
Thank you for your assistance.
Customer 452919, November 24th, 2024
Sociology
Thank you
Customer 452919, March 23rd, 2022
Humanities
Always excellent service, appreciate all the hard work
Customer 452995, January 20th, 2022
Nutrition, Hospitality & Human Services
Thank you for the revision.
Customer 452919, April 16th, 2024
Computer science
Thank You
Customer 453099, August 28th, 2022
11,595
Customer reviews in total
96%
Current satisfaction rate
3 pages
Average paper length
37%
Customers referred by a friend
OUR GIFT TO YOU
15% OFF your first order
Use a coupon FIRST15 and enjoy expert help with any task at the most affordable price.
Claim my 15% OFF Order in Chat