Project Management
June 7th, 2024
1.0You are managing a project and the original scope baseline of the project was budgeted at $100,000. since work on the project started there have been 13 authorized and approved changes to the project. The changes have a value of $12,000 and the cost of investigating them prior to their approval was $1,500. What is the current budget for the project?2. Your actual costs on your project are $75,000, the budget at completion is $100,000 and the earned value is $85,000. Your project has experienced some typical variances to date which has affected its financial performance but from this point forward you expect it to preform at the originally budgeted rate. What is your estimate at completion?