Reed Construction Ltd. (RCL) uses the percentage-of-completion method
January 5th, 2018
Reed Construction Ltd. (RCL) uses the percentage-of-completion method on its long-term construction contracts. In Year 16, RCL agreed to construct an apartment building for a contract price of $250 million. The job was completed in Year 18 with the following information:(in millions) Year 16 Year 17 Year 18Costs incurred to date $80 $165 $240Estimated costs to complete $150 $70 $0Billings to date $90 $180 $250Collections during the year $80 $95 $75What amount of the total contract price would be recognized as revenue in Year 17?