What is the critical path for the project using the normal time
June 8th, 2024
(20 pts) The following table shows the activities for a project.TIME (WEEKS)COST ($)ACTIVITYIMMEDIATE PREDECESSOR(S)NORMALCRASHNORMALCRASHAVAILABLE WEEKS OF CRASHINGCRASHING COST / WEEKAStart323,0003,300BStart648,0009,000CA114,0004,000DA543,5004,000EB434,7505,500FC222,0002,000GD114,0004,000HD,F323,5003,750IE,G323,0004,250JE215,0007,000FinishH, I, J——–Draw the network diagram.What is the critical path for the project using the normal time?Complete the table by filling the missing information.How many week(s) of crashing are available for activity E? Which activity should be crashed first?